Guatemala: El Triunfo prison surpasses 23% progress and approaches the structural phase after months of delays

rss · Infobae 2026-11-18T22:12:27Z es
The construction of El Triunfo Prison, Guatemala's future maximum-security facility, has surpassed 23% progress following the completion of a large portion of the earthworks and platform preparation. The Ministry of National Defense expects to begin the structural phase of the project within two to three weeks. The project is located in the department of Izabal and will have the capacity to house more than 2,000 inmates, including prisoners considered highly dangerous. The official goal is to hand the complex over to the Ministry of the Interior at the end of 2027, so that the Penitentiary System can take over its administration. The Minister of National Defense, Henry Sáenz, reported during a press conference in Zacapa that current work is focused on preparing the land on which the penitentiary facilities will be built. "As of today, we have a little more than 23% progress on the work. We are finishing all the earthworks, all the platforms, in order to begin the construction phase," the official stated. The project was delayed by an injunction and by rains The project's progress was conditioned by an injunction filed by the Municipality of Morales, in Izabal, which forced the temporary suspension of the work. According to Sáenz, that measure caused a delay of three to four months in the planned schedule. The Constitutional Court authorized the…
The construction of El Triunfo Prison in Izabal surpassed 23 percent progress after site preparation. (Archive/Ministry of Government) The construction of El Triunfo Prison, Guatemala's future maximum-security facility, surpassed 23% progress after the completion of much of the earthmoving and platform preparation work. The Ministry of National Defense expects to begin the structural phase of the project within two or three weeks. The project is located in the department of Izabal and will have the capacity to house more than 2,000 inmates, including prisoners considered highly dangerous. The official goal is to hand the complex over to the Ministry of Government at the end of 2027, so that the Penitentiary System can take over its administration. The Minister of National Defense, Henry Sáenz, reported during a press conference in Zacapa that current work is focused on preparing the land on which the penitentiary facilities will be built. The Ministry of National Defense expects to begin the structural phase of the prison within two or three weeks. (Archive/Government of Guatemala) "As of today, we have a little more than 23% progress on the work. We are finishing all the earthmoving, all the platforms, in order to begin the construction phase," the official said. The project's progress was conditioned by an injunction filed by the Municipality of Morales, in Izabal, which forced the temporary suspension of the work. According to Sáenz, that measure caused a delay of three to four months in the planned schedule. The Constitutional Court later authorized the continuation of the works. Following that ruling, the Ministry of National Defense resumed the site preparation work and the platforms for the construction of the buildings. Rain also affected the work on the site. The minister explained that, although the season had periods with less frequent rainfall, there were episodes of heavy intensity that hindered the progress of the ground work. Rainfall in the department of Izabal, in Guatemala, caused flooding and various damage. (Archive/Conred) On October 25, Sáenz had indicated that the construction phase would begin in January 2027. In his most recent update, he stated that this phase could begin within two or three weeks, once the earthmoving is completed. El Triunfo Prison was designed as a maximum-security prison, with infrastructure intended to reinforce the isolation and surveillance of inmates. The plan includes cast concrete walls, technological control systems, permanent monitoring, and constant surveillance. The complex will also have three external security rings. The first will be under the responsibility of the Ministry of National Defense; the second will correspond to the National Civil Police (PNC), and the third will be operated by a new guard force of the Penitentiary System. The distribution of functions seeks to establish differentiated controls over the perimeter and the interior of the penitentiary center. Once construction is completed, the Ministry of Government must organize the operation of the facility and define prisoner transfers. The prison will have cast concrete walls and three security rings distributed among the Army, the Police, and penitentiary guards. (Archive/Government of Guatemala) The authorities expect this to be the first maximum-security facility built in Guatemala in more than 40 years. The project is part of the government's strategy to expand penitentiary capacity, reduce overcrowding, and reinforce controls over persons deprived of liberty linked to criminal structures. The land where the prison is being built belonged to the El Triunfo farm, which passed into the hands of the State through the application of the Asset Forfeiture Law. The property had been linked to drug trafficker Mario Ponce. The ruling was issued by the Asset Forfeiture Court, where the current Minister of Government, Marco Antonio Villeda, served as judge. The State will now allocate the land to the construction of penitentiary infrastructure for highly dangerous inmates.

Translated from es by z-ai/glm-5.3-flash

Knowledge Graph

Entities
Highlight